Maintenance of Pipe Making Machine


1. After long-distance transport, bumps, loading or unloading. The screws and nuts of equipment may be loosening. Before installation, the equipment should be fastened again. And check the equipment carefully, to confirm the equipment in good condition.


2. After installation, the machine must be filled with enough lubrication oil when run this machine the first time. (remark : the reducer should be filled with number 46 machine oil.Gearbox inner arc gear,sprocket chain,wire rope should be filled with machine butter )


3. Raw materials must be in conformity with relevant requirements, There shouldn’t be hard granular materials and impurities which diameter is out of 10mm.


4. In the normal production process,worker should always check the machine carefully, to confirm whether the screws and nuts are loose, whether the lubrication point is the lack of oil.


5. Clean the equipment before and after work,maintain timely. And ensure that no waste material and residue is above the surface of mold and equipment.


6. The equipment should be placed in dry and ventilated house. In order to avoid rust and decay,defense rain and sunshine is necessary.


7. Under certain conditions of the equipment, correct adjustment operation is important factor of the pipe forming quality, During the normal production.Should check the motors, gearbox etc. often for overheating, running is normal or not.


8. Main shaft and pressure head connection must ensure up and down vertical,calibrated pressure angle.


9. When placing the mold, should put the support ring on the bottom of mold and ensure support ring and mold concentric.


10. Turn pressure head, adjust gap, make the pressure head drop to connect with support ring,make pressure head rotating,then put the mixed raw material into mold cavity, gradual increase in pressure head rotating,while gradually adding raw materials. Make all molding.


11. We should observe the tube billet and the mold movement during working process to check whether the forming quality is good, in the process of forming defects and faults should been adjust and eliminate at any time.


12. After pipe formed,tube and molds should be move out artificially, through artificial stripping out products, then a work cycle is completed.


13. The raw material of tube mixing should be uniform, the water should not be too large and should maintain good adhesion,the raw material should be mixed when use.


14. The transmission should be check regularly and refueling timely.
 

Leave Message

If you have any problems or questions about our products or need our support and assistance, please feel free to write us, we will reply to you within 24 hours, and never reveal your information to the third party. Thank you!

Subscribe to Updates

Subscribe to get latest news.

Capacity

Our company has 523 sets of various precision processing machine tools and advanced inspection and testing equipment; and produces 12,000 sets of various construction machinery annually.

Contact Us

Headquarters: Dazhuang Economic Development Zone, Yinan, Shandong, P.R. China Telephone:+8613663816343

Contact Us| Site Map