Precast concrete could mean better local roads in the future


Precast reinforced concrete. You may have never heard of it before, but you could be driving over it very soon if you use a specific Interstate 20 on ramp in the ArkLaTex.


"This is important because this is the first time we've done a project like this with the precast panels in the state of Louisiana. So we're forging new territory for this type of project," said Erin Buchanan, Louisiana Department of Transportation and Development spokeswoman.


The test area is the on-ramp to Interstate 20 heading eastbound right next to where U.S. Highway 79, U.S. Highway 80 and state Highway 169 intersect in Greenwood.


"So we ultimately replaced about 269 panels, concrete panels as part of this project about 1,200 feet of ramp," Buchanan said. 


It's very different from anything ever done in Louisiana before. Fully formed reinforced panels were installed and are ready to be driven on just as soon as they hit the dirt.

The ramp only had to be closed four weekends overnight to get the job done. In a traditional repair, it would have been closed for an entire month, seven days a week.


"There's some folks in the Federal Highway Administration that have had an interest in this for years. We've got a concept, we've got an idea. We've investigated it through the feasibility study. Let's try it out. Let's put some precast pavement on the road and let's see how it goes," said engineer David Merritt.


It's not a secret that there are a lot of roads in the ArkLaTex crumble too early. So what makes this specific on-ramp so important in terms of a testing ground for speed of construction and durability?


"The precast panels are really going to be put to the test in this particular location because of the amount of big truck traffic coming through. We're not talking about just passenger vehicles that are causing wear and tear on your roadway. These are a lot of 18-wheelers that are coming through. So in the next year, year and half or so will be able to really tell how this type of project is going to stand up against one of our more traditional projects," said Buchanan.


The ramp only had to be closed four weekends overnight to get the job done. In a traditional repair, it would have been closed for an entire month, seven days a week.


"There's some folks in the Federal Highway Administration that have had an interest in this for years. We've got a concept, we've got an idea. We've investigated it through the feasibility study. Let's try it out. Let's put some precast pavement on the road and let's see how it goes," said engineer David Merritt.


It's not a secret that there are a lot of roads in the ArkLaTex crumble too early. So what makes this specific on-ramp so important in terms of a testing ground for speed of construction and durability?


"The precast panels are really going to be put to the test in this particular location because of the amount of big truck traffic coming through. We're not talking about just passenger vehicles that are causing wear and tear on your roadway. These are a lot of 18-wheelers that are coming through. So in the next year, year and half or so will be able to really tell how this type of project is going to stand up against one of our more traditional projects," said Buchanan.


Some of those small doses could be on Interstate 20 through Bossier City. That prospect has a lot of people excited. DOTD says that if I-20 through Bossier City does get some much needed work involving precast concrete in the future it would be for smaller segments because of the expense.


In October, two of the local DOTD engineers are going to Washington D.C. for a panel discussion with engineers from other states who are also trying out the precast concrete process. They will be sharing their ideas and experiences to try and help improve the local highways.

Leave Message

If you have any problems or questions about our products or need our support and assistance, please feel free to write us, we will reply to you within 24 hours, and never reveal your information to the third party. Thank you!

Subscribe to Updates

Subscribe to get latest news.

Capacity

Our company has 523 sets of various precision processing machine tools and advanced inspection and testing equipment; and produces 12,000 sets of various construction machinery annually.

Contact Us

Headquarters: Dazhuang Economic Development Zone, Yinan, Shandong, P.R. China Telephone:+8613663816343

Contact Us| Site Map